Question 36
An example of a non-exchange revenue is
Question 37
A state grant will reimburse a city for 40% of the architectural, construction and project management costs to build an annex to a city building. A city employee, who is paid salary and benefits of 510,000 a month, works half-time on the project for six months.
The city reports the following project budgeted and actual costs:
Purpose Budget Actual
Architectural fees $ 100.000 $ 90,000
Construction costs $10,500,000 $10,000,000
Based upon the above information, what is the amount of allowable costs that the state will reimburse the city on the grant?
The city reports the following project budgeted and actual costs:
Purpose Budget Actual
Architectural fees $ 100.000 $ 90,000
Construction costs $10,500,000 $10,000,000
Based upon the above information, what is the amount of allowable costs that the state will reimburse the city on the grant?
Question 38
GASB establishes standards through a