Question 6
Your customer needs a compute solution. Their aging data center can only supply 5kW per rack, which is below the 15kW required for your planned solution.
Which change could you recommend to satisfy the requirement while maintaining the planned solution's level of performance? (Choose two.)
Which change could you recommend to satisfy the requirement while maintaining the planned solution's level of performance? (Choose two.)
Question 7
What is the appropriate use case for a traditional solution?
Question 8
Your customer acquired their Gen10 Plus servers through HPE GreenLake last year. They want to add HPE GreenLake for Block Storage to their GreenLake footprint. They ask you for a quote, and you inform them that you can start this process through their HPE GreenLake Central instance via a wizard-driven application.
What information do you need to gather for the wizard? (Choose two.)
What information do you need to gather for the wizard? (Choose two.)
Question 9
Which protocol should you recommend for a dedicated lossless fabric?
Question 10
You are designing a new datacenter solution for a customer with a limited power footprint.
Which tools can you use to present the power consumption of proposed solution to the customer? (Choose two.)
Which tools can you use to present the power consumption of proposed solution to the customer? (Choose two.)