Question 196

During a Stage 1 audit opening meeting, the Management System Representative (MSR) asks to extend the audit scope to include a new site overseas which they have expanded into since the certification application was made.
Select two options for how the auditor should respond.
  • Question 197

    You are an ISMS audit team leader tasked with conducting a follow-up audit at a client's data centre.
    Following two days on-site you conclude that of the original 12 minor and 1 major nonconformities that prompted the follow-up audit, only 1 minor nonconformity still remains outstanding.
    Select four options for the actions you could take.
  • Question 198

    Information has a number of reliability aspects. Reliability is constantly being threatened. Examples of threats are: a cable becomes loose, someone alters information by accident, data is used privately or is falsified.
    Which of these examples is a threat to integrity?
  • Question 199

    You are an experienced ISMS audit team leader conducting a third-party surveillance visit.
    You notice that although the auditee is claiming conformity with ISO/IEC 27001:2022 they are still referring to Improvement as clause 10.2 (as it was in the 2013 edition) when this is now clause 10.1 in the 2022 edition. You have confirmed they are meeting all of the 2022 requirements set out in the standard.
    Select one option of the action you should take.
  • Question 200

    You are an experienced ISMS audit team leader. An auditor in training has approached you to ask you to clarify the different types of audits she may be required to undertake.
    Match the following audit types to the descriptions.
    To complete the table click on the blank section you want to complete so that It is highlighted In fed, and then click on the applicable text from the options below. Alternatively, you may drag and drop each option to the appropriate blank section.