Question 136

You are conducting a third-party surveillance audit when another member of the audit team approaches you seeking clarification. They have been asked to assess the organisation's application of control 5.7 - Threat Intelligence. They are aware that this is one of the new controls introduced in the 2022 edition of ISO/IEC
27001, and they want to make sure they audit the control correctly.
They have prepared a checklist to assist them with their audit and want you to confirm that their planned activities are aligned with the control's requirements.
Which three of the following options represent valid audit trails?
  • Question 137

    You are a certification body auditor, conducting a surveillance audit to ISO/IEC 27001:2022 of a data centre operated by a client who provides hosting services for ICT facilities.
    You and your guide are currently in one of the private suites that the client rents out to customers. Access to each suite is controlled using a combination lock. CCTV is also installed in every suite.
    Within each suite are three data cabinets in which the client can locate mission-critical servers and other items of networking equipment such as switches and routers.
    You notice that whilst two of the cabinets in your suite are locked, the third is unlocked. You ask the guide why. They reply "This is because the client is currently swapping out a hard drive unit. Their technician is currently on a lunch break".
    What three actions should you undertake next?
  • Question 138

    Which of the following is a possible event that can have a disruptive effect on the reliability of information?
  • Question 139

    You are performing an ISMS initial certification audit at a residential nursing home that provides healthcare services. The next step in your audit plan is to conduct the closing meeting. During the final audit team meeting, as an audit team leader, you agree to report 2 minor nonconformities and 1 opportunity for improvement as below:

    Select one option of the recommendation to the audit programme manager you are going to advise to the auditee at the closing meeting.
  • Question 140

    You are an ISMS audit team leader tasked with conducting a follow-up audit at a client's data centre.
    Following two days on-site you conclude that of the original 12 minor and 1 major nonconformities that prompted the follow-up audit, only 1 minor nonconformity still remains outstanding.
    Select four options for the actions you could take.