Question 86
You are an experienced ISMS audit team leader who is currently conducting a third party initial certification audit of a new client, using ISO/IEC 27001:2022 as your criteria.
It is the afternoon of the second day of a 2-day audit, and you are just about to start writing your audit report.
So far no nonconformities have been identified and you and your team have been impressed with both the site and the organisation's ISMS.
At this point, a member of your team approaches you and tells you that she has been unable to complete her assessment of leadership and commitment as she has spent too long reviewing the planning of changes.
Which one of the following actions will you take in response to this information?
It is the afternoon of the second day of a 2-day audit, and you are just about to start writing your audit report.
So far no nonconformities have been identified and you and your team have been impressed with both the site and the organisation's ISMS.
At this point, a member of your team approaches you and tells you that she has been unable to complete her assessment of leadership and commitment as she has spent too long reviewing the planning of changes.
Which one of the following actions will you take in response to this information?
Question 87
An organisation is looking for management system initial certification. Please identify the sequence of the activities to be undertaken by the organisation.
To complete the sequence click on the blank section you want to complete so that it is highlighted in red, and then click on the applicable text from the options below. Alternatively, you may drag and drop the options to the appropriate blank section.

To complete the sequence click on the blank section you want to complete so that it is highlighted in red, and then click on the applicable text from the options below. Alternatively, you may drag and drop the options to the appropriate blank section.

Question 88
In acceptable use of Information Assets, which is the best practice?
Question 89
Which of the following is a possible event that can have a disruptive effect on the reliability of information?
Question 90
You are performing an ISMS audit at a residential nursing home that provides healthcare services.
The next step in your audit plan is to verify the information security incident management process.
The IT Security Manager presents the information security incident management procedure (Document reference ID:ISMS_L2_16, version 4).
You review the document and notice a statement "Any information security weakness, event, and incident should be reported to the Point of Contact (PoC) within 1 hour after identification". When interviewing staff, you found that there were differences in the understanding of the meaning of the phrase "weakness, event, and incident".
The IT Security Manager explained that an online "information security handling" training seminar was conducted 6 months ago. All the people interviewed participated in and passed the reporting exercise and course assessment.
You would like to investigate other areas further to collect more audit evidence. Select three options that would not be valid audit trails.
The next step in your audit plan is to verify the information security incident management process.
The IT Security Manager presents the information security incident management procedure (Document reference ID:ISMS_L2_16, version 4).
You review the document and notice a statement "Any information security weakness, event, and incident should be reported to the Point of Contact (PoC) within 1 hour after identification". When interviewing staff, you found that there were differences in the understanding of the meaning of the phrase "weakness, event, and incident".
The IT Security Manager explained that an online "information security handling" training seminar was conducted 6 months ago. All the people interviewed participated in and passed the reporting exercise and course assessment.
You would like to investigate other areas further to collect more audit evidence. Select three options that would not be valid audit trails.