Question 126

Scenario 9: OpenTech provides IT and communications services. It helps data communication enterprises and network operators become multi-service providers During an internal audit, its internal auditor, Tim, has identified nonconformities related to the monitoring procedures He identified and evaluated several system Invulnerabilities.
Tim found out that user IDs for systems and services that process sensitive information have been reused and the access control policy has not been followed After analyzing the root causes of this nonconformity, the ISMS project manager developed a list of possible actions to resolve the nonconformity. Then, the ISMS project manager analyzed the list and selected the activities that would allow the elimination of the root cause and the prevention of a similar situation in the future. These activities were included in an action plan The action plan, approved by the top management, was written as follows:
A new version of the access control policy will be established and new restrictions will be created to ensure that network access is effectively managed and monitored by the Information and Communication Technology (ICT) Department The approved action plan was implemented and all actions described in the plan were documented.
Based on this scenario, answer the following question:
OpenTech has decided to establish a new version of its access control policy. What should the company do when such changes occur?
  • Question 127

    Scenario 8: SunDee is an American biopharmaceutical company, headquartered in California, the US. It specializes in developing novel human therapeutics, with a focus on cardiovascular diseases, oncology, bone health, and inflammation. The company has had an information security management system (ISMS) based on SO/IEC 27001 in place for the past two years. However, it has not monitored or measured the performance and effectiveness of its ISMS and conducted management reviews regularly Just before the recertification audit, the company decided to conduct an internal audit. It also asked most of their staff to compile the written individual reports of the past two years for their departments. This left the Production Department with less than the optimum workforce, which decreased the company's stock.
    Tessa was SunDee's internal auditor. With multiple reports written by 50 different employees, the internal audit process took much longer than planned, was very inconsistent, and had no qualitative measures whatsoever Tessa concluded that SunDee must evaluate the performance of the ISMS adequately. She defined SunDee's negligence of ISMS performance evaluation as a major nonconformity, so she wrote a nonconformity report including the description of the nonconformity, the audit findings, and recommendations. Additionally, Tessa created a new plan which would enable SunDee to resolve these issues and presented it to the top management According to scenario 8, Tessa created a plan for ISMS monitoring and measurement and presented it to the top management Is this acceptable?
  • Question 128

    Scenario 5: Operaze is a small software development company that develops applications for various companies around the world. Recently, the company conducted a risk assessment to assess the information security risks that could arise from operating in a digital landscape. Using different testing methods, including penetration Resting and code review, the company identified some issues in its ICT systems, including improper user permissions, misconfigured security settings, and insecure network configurations. To resolve these issues and enhance information security, Operaze decided to implement an information security management system (ISMS) based on ISO/IEC 27001.
    Considering that Operaze is a small company, the entire IT team was involved in the ISMS implementation project. Initially, the company analyzed the business requirements and the internal and external environment, identified its key processes and activities, and identified and analyzed the interested parties In addition, the top management of Operaze decided to Include most of the company's departments within the ISMS scope. The defined scope included the organizational and physical boundaries. The IT team drafted an information security policy and communicated it to all relevant interested parties In addition, other specific policies were developed to elaborate on security issues and the roles and responsibilities were assigned to all interested parties.
    Following that, the HR manager claimed that the paperwork created by ISMS does not justify its value and the implementation of the ISMS should be canceled However, the top management determined that this claim was invalid and organized an awareness session to explain the benefits of the ISMS to all interested parties.
    Operaze decided to migrate Its physical servers to their virtual servers on third-party infrastructure. The new cloud computing solution brought additional changes to the company Operaze's top management, on the other hand, aimed to not only implement an effective ISMS but also ensure the smooth running of the ISMS operations. In this situation, Operaze's top management concluded that the services of external experts were required to implement their information security strategies. The IT team, on the other hand, decided to initiate a change in the ISMS scope and implemented the required modifications to the processes of the company.
    Based on the scenario above, answer the following question:
    What led Operaze to implement the ISMS?
  • Question 129

    Based on scenario 9. the top management decided to accept the risk related to a nonconformity to control 5.17 Authentication informal ion. is this acceptable?
  • Question 130

    Scenario 6: Skyver offers worldwide shipping of electronic products, including gaming consoles, flat-screen TVs. computers, and printers. In order to ensure information security, the company has decided to implement an information security management system (ISMS) based on the requirements of ISO/IEC 27001.
    Colin, the company's best information security expert, decided to hold a training and awareness session for the personnel of the company regarding the information security challenges and other information security-related controls. The session included topics such as Skyver's information security approaches and techniques for mitigating phishing and malware.
    One of the participants in the session is Lisa, who works in the HR Department. Although Colin explains the existing Skyver's information security policies and procedures in an honest and fair manner, she finds some of the issues being discussed too technical and does not fully understand the session. Therefore, in a lot of cases, she requests additional help from the trainer and her colleagues Based on scenario 6. Lisa found some of the issues being discussed in the training and awareness session too technical, thus not fully understanding the session. What does this indicate?