Question 21

A company is analysing its existing product's components and aims at reducing costs without damaging customer value proposition. They want to check which components are critical and which are unnecessary. Which of the following should be adopted by the company?
  • Question 22

    Honda of America Manufacturing is a well established automobile manufacturer. It purchases tens of thousands of materials and parts from suppliers, however, only few of them are strategic. To these suppliers, Honda's procurement manager requires them to send details of labour, materials, overhead cost and profit. However, the suppliers are reluctant to submit such confidential infor-mation. Is the procurement manager's action appropriate?
  • Question 23

    Which of the following is the core of value analysis process?
  • Question 24

    Which of the following agencies can produce a technical standard?
  • Question 25

    Which of the following is the process for improving the value of a new product or service?