Question 66

You are the production scheduler at a manufacturing company. You schedule estimated production orders and ensure that capacity is used efficiently.
You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

Question 67

A manufacturer uses discreet orders and manually consumes raw material after reporting products as finished.
You are performing an end-of-month closing for remaining picking lists on production orders. You must not be required to consume the full amount of material on production order picking lists as a result of improved production efficiency. When the production manager verifies that no material is left to consume, there are remaining back-ordered amounts.
You need to pick the line item short and eliminate the remaining demand.
What should you do?
  • Question 68

    You are the quality assurance manager of a pharmaceuticals company.
    One of your customers has requested to only receive batches of item B0001 that have an acid concentration between 5.5% -10.5%.
    You need to set up the customer specific batch attribute to track percent acid for B0001.
    Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

    Question 69

    You are the production supervisor in charge of setting effective cost prices for the labor force in a manufacturing company. It is the end of the year and the labor rates have been recalculated based on new salary dat a. You need to update the effective labor costs for all labor groups.
    Which element must be updated?
  • Question 70

    You produce 100 total units of finished goods. The amount of material used to produce the goods is the equivalent amount of material needed to produce 105 finished goods.
    The company must track variances in material compared to the original estimated amount. You must only use one picking list journal for each production order.
    You need to post a picking list that accounts for the material required to produce 105 finished goods.
    What should you do?