Question 6

A company uses Dynamics 365 for Finance and Operations for Process manufacturing.
You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order.
You need to optimize the planned production orders.
What should you do?
  • Question 7

    You are the product design manager for a computer manufacturer.
    Your new laptop model is configurable. There are restrictions on which hardware components can be selected depending on the model. You create configuration groups for hardware and software.
    You need to create a new laptop item number and configurations.
    In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.

    Question 8

    A glass bottle manufacturer uses route operations to schedule resources and track manufacturing costs.
    The company has recently seen an increase in demand and purchases another resource. The company uses the same costs per resource. However, the new resource costs more to run. The company must be able to track cost contributions for the new resource.
    You need to create a cost category for the new resource.
    Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
    NOTE: Each correct selection is worth one point.

    Question 9

    A manufacturer produces HDMI cables. Typically, the item is manufactured.
    The manufacturer will occasionally buy unbranded HDMI cables from a vendor in order to keep up with demand. The company must use the same item number whether they make or buy the item.
    What should you do?
  • Question 10

    A Discrete manufacturing company produces speakers. The high-end speaker model uses protective rubber strips on the edges.
    Approximately five inches of rubber is consistently scrapped in the production process, regardless of production quantity. Workers manually consume the extra material on the picking list or scrap it in an inventory journal.
    You need configure the system to automatically account for this scrap on the Bill of materials (BOM).
    What should you do?