Question 66

A distribution company uses Dynamics 365 Supply Chain Management
Users in the warehouse must have the ability to create process transfer orders from a mobile device.
You need to complete setup.
Which areas should you configure?

Question 67

Drag and Drop Question
A company wants to expand their purchasing power by enhancing their current procurement catalog in Dynamics 365 Supply Chain Management.
The company wants to redirect to external websites to help build their purchase requisitions.
You need to set up an external catalog.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question 68

You are a functional consultant for a company named Contoso Entertainment System USA (USMF).
You need to configure a new quality process for item number M0017. The process must meet the following requirements:
Perform an impedance test on 100 percent of the units purchased.
Initiate the test after the product receipt is posted.
To complete this task, sign in to Dynamics 365 portal.
  • Question 69

    You are a functional consultant for a company named Contoso Entertainment System USA (USMF).
    You need to regenerate a master plan named DynPlan for item number D0023.
    To complete this task, sign in to Dynamics 365 portal.

    Question 70

    Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
    After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
    A process manufacturer is implementing Dynamics 365 Supply Chain Management to produce sports energy bars, beverages, and nutritional supplements.
    The company must run a series of quality control tests for all its beverage items for each production run after the items are completed from a production job The testing process for all beverages must follow the same process. The energy bars and nutritional supplements have their own testing requirements.
    The specific tests are not yet defined.
    You need to configure the quality associations in preparation for the requirements.
    Solution: Create a quality association for each item with Reference type as Inventory, using item code as Table and specifying each item on the quality associations. Set Event type to Report as finished. Set Execution to After.
    Does the solution meet the goal?