Question 66
You are the production scheduler for a manufacturing company. You have run the Resource Group Capacity report as shown in the Resource Group 21 Capacity exhibit. (Click the Resource Group 21 Capacity tab).

After reviewing that report, you run Resource Capacity reports as shown in the Resource 2101 and 2102 Capacity exhibits. (Click the 2101 Capacity and 2102 Capacity tabs.)

You run the Gantt chart report as shown in the Gantt exhibit to determine the production orders scheduled on the resources. (Click the Gantt tab.)

You need to determine the method to schedule the production lines.

For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.


After reviewing that report, you run Resource Capacity reports as shown in the Resource 2101 and 2102 Capacity exhibits. (Click the 2101 Capacity and 2102 Capacity tabs.)

You run the Gantt chart report as shown in the Gantt exhibit to determine the production orders scheduled on the resources. (Click the Gantt tab.)

You need to determine the method to schedule the production lines.

For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.

Question 67
A company uses multiple Dynamics 365 applications to track and repair equipment.
The company wants to improve its repair order process. Repair technicians frequently encounter unexpected issues daily. The technicians must be empowered to address the issues and create new work orders by doing the following:
* Provide step-by-step, just-in-time training for work order completion in the field by using videos and text.
* Document work order creation in a single, printable document.
* Report on the use of hands-on training.
You need to implement a solution forth requirements.
Which solution should you implement for each requirement? To answer, drag the appropriate solutions to the correct requirements. Each solution may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

The company wants to improve its repair order process. Repair technicians frequently encounter unexpected issues daily. The technicians must be empowered to address the issues and create new work orders by doing the following:
* Provide step-by-step, just-in-time training for work order completion in the field by using videos and text.
* Document work order creation in a single, printable document.
* Report on the use of hands-on training.
You need to implement a solution forth requirements.
Which solution should you implement for each requirement? To answer, drag the appropriate solutions to the correct requirements. Each solution may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

Question 68
A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.
An employee discovers an error after a time and attendance record is approved and transferred. The payroll transfer has not been run. However, the time has been posted against the production order.
You need to reverse the transferred registrations.
What happens to the production order time posting?
An employee discovers an error after a time and attendance record is approved and transferred. The payroll transfer has not been run. However, the time has been posted against the production order.
You need to reverse the transferred registrations.
What happens to the production order time posting?
Question 69
You are the production scheduler at a manufacturing company. You schedule estimated production orders and ensure that capacity is used efficiently.
You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

Question 70
A manufacturer is implementing Dynamics 365 Supply Chain Management with warehouse management processes (WMS).
Warehouse workers use hand-held devices to pick and stage batch-tracked products for production. The warehouse manager requires that products are removed from on-hand inventory and consumed when they are picked and staged for production.
You need to remove the products from on-hand inventory.
What should you configure?
Warehouse workers use hand-held devices to pick and stage batch-tracked products for production. The warehouse manager requires that products are removed from on-hand inventory and consumed when they are picked and staged for production.
You need to remove the products from on-hand inventory.
What should you configure?