Question 11

NACE International Standards are developed by:
  • Question 12

    In powder coatings, when the particles of powder begin to flow but are not fully liquid, they are in what stage?
  • Question 13

    You are the NACE Inspector on a project where a stationary floating structure is being coated and you notice a self-smoothing anti-fouling coating has been specified.
    This is not a good choice because:
  • Question 14

    Linings are used on the interior of pipelines to
  • Question 15

    You are NACE Level 2 Inspector working on a tank lining job where a mobile centrifugal blast unit is being used to blast the tank floor to a NACE No.1/SSPC SP 5. The Contractor has completed his final blast and has called for a hold point inspection. This is the 1 st time you have seen field based centrifugal blast cleaning. You observe what appears to be staining on the substrate however the Contractor assures you this is normal when using centrifugal blast units and what you are seeing is what is defined in the standard as an acceptable variation in appearance.
    Your FIRST preferred course of action is to: