Question 26
A customer has a G6 AHV cluster with 4x10GbE NICs on each node and the following configuration:
* Networking is set to default
* Only two NICs are connected
The customer receives the following critical message:
The NIC is disconnected from the switch, or the switchport is failing.
What should the consultant verify to resolve the issue?
* Networking is set to default
* Only two NICs are connected
The customer receives the following critical message:
The NIC is disconnected from the switch, or the switchport is failing.
What should the consultant verify to resolve the issue?
Question 27
A consultant is installing Nutanix AOS on Cisco UCS.
Which method should be used to install AOS on UCS hardware platforms?
Which method should be used to install AOS on UCS hardware platforms?
Question 28
In a 20-node ESXi deployment, the customer needs additional resiliency to survive the loss of two nodes concurrently.
Which configuration should the consultant use to ensure that the appropriate resources are available?
Which configuration should the consultant use to ensure that the appropriate resources are available?
Question 29
A consultant creates an AHV cluster and connects the Intel X550T NICs to the top of rack switch using Twinax cables. The activity and link lights are green. The cluster cannot communicate over the 10GbE link.
What is the first command the consultant should perform to troubleshoot the issue?
What is the first command the consultant should perform to troubleshoot the issue?
Question 30
An administrator has a custom backup application that requires a 2TB disk and runs in Windows. Throughput is considerably lower than expected.
The application was installed on a VM with the following configuration:
* Four vCPUs with one core/vCPU
* 4GB of Memory
* One 50GB vDisk for the Windows installation
* One 2TB vDisk for the application
What is the recommended configuration change to improve throughput?
The application was installed on a VM with the following configuration:
* Four vCPUs with one core/vCPU
* 4GB of Memory
* One 50GB vDisk for the Windows installation
* One 2TB vDisk for the application
What is the recommended configuration change to improve throughput?