Question 96
Scenario: Turbonix Enterprises
Please read this scenario prior to answering the question
Turbonix Enterprises specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. Turbonix has manufacturing facilities located in Palm Springs, California, Omaha, Nebraska, and Winnipeg, Manitoba. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturer's design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and greatly improved blade longevity. Turbonix has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
Turbonix has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Review Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
Turbonix has used T0GAF and its Architecture Development Method (ADM) to develop its automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies. They have adapted their Enterprise Architecture to closely follow the TOGAF 9 framework. All of Turbonix's enterprise architects have been trained and certified on TOGAF 9.Recently, an architecture project was completed that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Manufacturing Architecture Board approved the plan for immediate implementation at each plant.
An Architecture Contract was developed that detailed the work needed to implement and deploy the new Automated Test System controller. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each site to ensure consistency.
Refer to the Turbonix Enterprises Scenario
You are the Lead Architect for this activity.
You have been asked to recommend the best approach to adopt to address the Chief Engineer's concern.
Based on TOGAF 9, which of the following is the best answer?
Please read this scenario prior to answering the question
Turbonix Enterprises specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. Turbonix has manufacturing facilities located in Palm Springs, California, Omaha, Nebraska, and Winnipeg, Manitoba. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturer's design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and greatly improved blade longevity. Turbonix has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
Turbonix has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Review Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
Turbonix has used T0GAF and its Architecture Development Method (ADM) to develop its automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies. They have adapted their Enterprise Architecture to closely follow the TOGAF 9 framework. All of Turbonix's enterprise architects have been trained and certified on TOGAF 9.Recently, an architecture project was completed that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Manufacturing Architecture Board approved the plan for immediate implementation at each plant.
An Architecture Contract was developed that detailed the work needed to implement and deploy the new Automated Test System controller. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each site to ensure consistency.
Refer to the Turbonix Enterprises Scenario
You are the Lead Architect for this activity.
You have been asked to recommend the best approach to adopt to address the Chief Engineer's concern.
Based on TOGAF 9, which of the following is the best answer?
Question 97
Which of the following describes a purpose of an Architecture Compliance review?
Question 98
When using a cycle of the ADM to establish an Architecture Capability as described in TOGAF Part VII, which architecture would describe the infrastructure requirements?
Question 99
Which one of the following is an objective of Phase A of the TOGAF ADM?
Question 100
Which one of the following best describes the purpose of a Change Request?