Question 1

Team Alpha completed 30 "points" of work in two weeks. Team Beta completed 10 "points" of work in one week. Which team delivered more value?
Response:

Question 2

True or False: When many agile teams are working on different products, they should create a common status reporting dashboard of work performed in order for management to understand the status of each team.
Response:

Question 3

Over a million customers use BLOOM company's product. BLOOM recently implemented and released a particular feature that they believed would be widely adopted by the users.
After gathering enough data from the test, it is concluded that the feature functions as intended however the usage rate was surprisingly low.
What should BLOOM do?
Response:

Question 4

Your executive sponsor visits the executives of an important customer. During the visit, they communicate to her what they believe is an important feature for your next product release, and your sponsor promises it will be in the release.
Your team builds and delivers the feature as promised. Over the next three months, your measures of the usage of the feature show that it has not been used. When you ask users from this important customer "why?", they indicate that they did not need the feature and their executives don't really understand the needs of their users.
Do you communicate this to your executive sponsor?
(choose the best answer)
Response:

Question 5

An organisation has a large number of products and is unsure about how to allocate funding across the products. Which of the following is the best way for them to proceed?
Response: