Question 1

A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities.
The constraint described in this scenario is:

Question 2

A project manager receives an initial project assignment.
Which of the following documents is MOST likely to indicate the organizational structure for the project?

Question 3

Which of the following is an example of a project?

Question 4

A project team is analyzing the risk register and identifies several issues that may be related to potential instability of the accounting system. Which of the following should be addressed so risk responses will be more effective?

Question 5

When a project team member completes a task in the WBS, which of the following are the primary recipients of the notification? (Choose two.)