Question 1

A team member has been consistently underperforming, and mentoring has not corrected the problem.
Which of the following actions should the project manager take?

Question 2

A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project's success?

Question 3

A contract review meeting has been scheduled with a non-performing vendor. The project manager has been asked to provide recommendations for continuous service improvements and removal of the vendor. Which of the following documents should the project manager review BEFORE the meeting?

Question 4

Company A and Company B have come together to form a new Company C.
Staff members from both companies have been moved to Company C, and there are rumors that some staff might be asked to leave.
These are examples of: (Choose two.)

Question 5

A firm, fixed-price project is on pace to exceed the maximum defect rate identified in the project charter. The customer has stated the project must be delivered on time.
Which of the following is the BEST option for the project to complete on time and within parameters?