Question 151
A project manager notices a lack of meeting attendance from the project team. Which of the following actions might the project manager take to BEST improve the level of attendance?
Question 152
The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?
Question 153
A project manager at a projectized organization is finishing the objective goals for the appraisal process. Performance goals have been identified for colocated individuals working on the team. Which of the following is the appropriate communication method for relaying the goals to the team members?
Question 154
A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave.
Which of the following should a project manager update to document this information?
Which of the following should a project manager update to document this information?
Question 155
Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project's current status.
Which of the following types of reports should the project sponsor use to quickly summarize the status report data?
Which of the following types of reports should the project sponsor use to quickly summarize the status report data?