Question 301

A project requires daily status updates.
Which of the following is the MOST effective method for providing these updates?
  • Question 302

    A project manager is creating the WBS.
    In which of the following phases is the project?
  • Question 303

    A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it.
    Which of the following steps of the control was missed?
  • Question 304

    A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule. Which of the following should the project manager do NEXT?
  • Question 305

    A PM notes a feature that was delivered does not appear in the latest requirement document. The PM immediately submits a change request for remediation. Which of the following actions has the PM omitted?