Question 46

A sensitive project requires activities to occur with very specific, to-the-minute timing. Which of the following would BEST ensure on-time delivery?
  • Question 47

    An active project has a CPI of 0.92. Which of the following can be determined?
  • Question 48

    Two team members approach a project manager with different ideas for completing a task. After listening to the team members' ideas, the project manager does not choose either one and requires both members to finish the task as originally planned. Which of the following conflict resolution techniques is the project manager applying?
  • Question 49

    Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3.
    Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?
  • Question 50

    A critical stakeholder has requested additional status updates beyond the schedule Which of the following factors MOST likely needs to be accounted for when communicating with this stakeholder?