Question 1
During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?
Question 2
A company accepts a proposal from a third-party vendor to provide staffing. Which of the following documents should the project manager create NEXT?
Question 3
Which of the following is the BEST source for identifying the defect tolerance of a project?
Question 4
A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?
Question 5
Which of the following documents need to be updated as events occur during a project?
(Select TWO).
(Select TWO).