Question 106

Which of the following roles has approval authority for project funding?
  • Question 107

    A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?
  • Question 108

    A project requires daily status updates.
    Which of the following is the MOST effective method for providing these updates?
  • Question 109

    There are four parallel paths on a network diagram. The summary duration of each path is below:
    A, C, G: 10 weeks
    A, B, F: 8 weeks
    D, E, H: 12 weeks
    D, B, F: 7 weeks
    Which of the following tasks are on the critical path?
  • Question 110

    A company hires an outside vendor to provide 24/7 support.
    Which of the following documents would determine the contractual obligations?