Question 51

A project manager is releasing resources and archiving documents. Which of the following phases is the project MOST likely in?
  • Question 52

    A project manager is collecting work package information from the project team for the first time.
    Which of the following elements should the project manager have at the end of the meeting?
  • Question 53

    A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:
    Project description
    Draft project timeline and schedule
    Rough milestones
    Draft project budget
    Draft resources required
    High-level risk review
    Which of the following sections should be included in this document?
  • Question 54

    Which of the following is an attribute of a potential project?
  • Question 55

    A vendor is unable to deliver an order by the specified date.
    Which of the following should be the project manager's NEXT steps? (Choose two.)