Question 191

Task A has a duration of 2 days and is a predecessor of task B, which has a duration of 3 days and is a predecessor of task C.
Task C has a duration of 4 days. Task D has a start-to-start relationship with task A and a duration of 11 days. Which of the following is the lag time for task D?
  • Question 192

    Which of the following is the MOST appropriate communication method for a highly confidential message to a Multilanguage global project team?
  • Question 193

    A project team received a memo stating no one can come into the office for the rest of the week due to heavy forecasted rain. The projected team reviews the risk management plan and carries out the risk response. The memo that prompted the activation of the risk response is referred to as the:
  • Question 194

    Which of the following will identify the MOST potential project risks?
  • Question 195

    One deliverable failed during testing, and this has already happened several times.
    Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?