Question 16
Two highly skilled resources, who are currently working on other projects, are assigned to a project manager. Personality conflicts between the two resources have adversely affected project completion. The project manager has asked a manager with direct authority over the resources to provide input to resolve the issue, but the project manager does not have the level of authority required to resolve the personality conflict.
Which of the following structure types is this an example of?
Which of the following structure types is this an example of?
Question 17
During a CCB, a SME evaluated the impact and provided new information because of business process changes for handling potential failure. Which of the following documents should be updated?
Question 18
Which of the following documents is typically signed by the vendor and includes a reference for how customers' internal information will be protected?
Question 19
During a meeting, the project manager abruptly interrupts the discussion of two team members who have not reached an agreement on a particular requirement and continues with the meeting.
Which of the following conflict resolutions is the project manager performing?
Which of the following conflict resolutions is the project manager performing?
Question 20
A number of requirements, conflicts, and reworks during a project delayed the schedule, increased the budget, and required replanning efforts.
Which of the following is MOST likely the cause?
Which of the following is MOST likely the cause?