Question 16

A key stakeholder asked several members of the project team to make project changes without submitting them for approval. Because the stakeholder is related to the Chief Executive Officer (CEO), the team members are reluctant to deny these requests. Which of the following should the project manager do FIRST to control this situation?
  • Question 17

    A project manager has been assigned a complex project and does not know all the activities required to complete it.
    Which of the following if the BEST approach to determine the work packages for the WBS?
  • Question 18

    Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?
  • Question 19

    A concrete pad needs to be laid for a new house and requires three days to cure. The project manager notes that rain may be in the immediate forecast.
    Which of the following would BEST avoid the risk of rain damage?
  • Question 20

    A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation. Which of the following documents should the project manager examine NEXT to provide an explanation?