Question 21

Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?
  • Question 22

    A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).
  • Question 23

    A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

    Which of the following is the current status of the process?
  • Question 24

    Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?
  • Question 25

    Which of the following criteria would favor using the agile methodology to manage an upcoming project?