Question 111
Which of the following BEST describes how an organization should coordinate management of multiple related projects?
Question 112
A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?
Question 113
During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.
INSTRUCTIONS
Review the email with the latest updates sent by the project sponsor and respond in the following order:
1. Select the best tool for tracking the server migration progress.
2. Select the new critical path.
3. Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Select the Appropriate Tool:





Select the new critical path.
Option A

Option B

Option C


INSTRUCTIONS
Review the email with the latest updates sent by the project sponsor and respond in the following order:
1. Select the best tool for tracking the server migration progress.
2. Select the new critical path.
3. Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Select the Appropriate Tool:





Select the new critical path.
Option A

Option B

Option C


Question 114
A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?
Question 115
A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the
manufacturer. The delay will cause the project to be significantly behind schedule. The project manager
decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the
following risk management approaches has the project manager taken?
manufacturer. The delay will cause the project to be significantly behind schedule. The project manager
decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the
following risk management approaches has the project manager taken?