Question 161

Given the following network diagram:
Which of the following is the critical path?
Question 162
Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
Question 163
A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project
sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the
implementation and validation in production. During cutover, the team runs into a validation issue after 2.5
hours, and the process is only 70% through the validation steps Which of the following actions should the
project manager take?
sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the
implementation and validation in production. During cutover, the team runs into a validation issue after 2.5
hours, and the process is only 70% through the validation steps Which of the following actions should the
project manager take?
Question 164
While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?
Question 165
During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.
INSTRUCTIONS
Review the email with the latest updates sent by the project sponsor and respond in the following order:
1. Select the best tool for tracking the server migration progress.
2. Select the new critical path.
3. Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Select the Appropriate Tool:





INSTRUCTIONS
Review the email with the latest updates sent by the project sponsor and respond in the following order:
1. Select the best tool for tracking the server migration progress.
2. Select the new critical path.
3. Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Select the Appropriate Tool: