Question 56

You are a Microsoft Power Platform architect.
You need to design a process to transport configuration and test data from one environment to a separate environment Which four actions should you recommend be performed in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question 57

You are creating a scope of work document for a solution. You have the following requirements:
* Track support cases, first response time, and resolution time.
* Include a chat-like interface that allows managers to check the status of cases with minimal manual searching.
* Allow cases to have multiple different priority levels.
You need to include the required Dynamics 365 and Microsoft Power Platform components. Which two components should you include? Each correct answer presents part of the solution.
NOT: Each correct selection is worth one point.
  • Question 58

    You are designing a Microsoft Power Platform solution for an automobile parts manufacturer. You create the following tables:

    You need to recommend a relationship behavior.
    Which relationship behavior should you recommend?