Question 196

Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this.
What should the agile practitioner do?
  • Question 197

    A large project team is assigned to a complex technical project with many interdependent epics. The team starts to experience problems in the second sprint as the technical leads are independently unable to determine the needed solutions.
    What should the project lead do to help the team?
  • Question 198

    During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.
    What should the project leader do?
  • Question 199

    When an Agile project team receives an "emergency request" during an iteration, which is the best first step that the Agile project manager should take?
  • Question 200

    For a critical project, a new team has been formed from various departments. The project manager should start team building by: