Question 266
Following chart lists stories for a release of an Agile project;

If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the team's velocity?

If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the team's velocity?
Question 267
At the end of first iteration, the team finishes User Stories A, Band 50% of C. What is the team velocity?


Question 268
An agile team provides feedback that user stories include insufficient details to understand the requirements.
What should the agile practitioner do?
What should the agile practitioner do?
Question 269
A full cycle of design-code-verifyrelease practiced by extreme Programming (XP) teams is called:
Question 270
An agile coach is assigned to help a project team that was recently co-located close to a very popular business Many team members visit this business during working hours which affects team performance.
What should the agile coach do to mitigate this issue?
What should the agile coach do to mitigate this issue?