Question 86
A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting The stakeholder insists that these requirements must be taken into account despite time and budget constraints.
What is the most effective way to manage this situation?
What is the most effective way to manage this situation?
Question 87
A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix.
Which of the following is the best strategy to define the appropriate acceptance criteria?
Which of the following is the best strategy to define the appropriate acceptance criteria?
Question 88
A business analyst from Company A has been assigned a project to document and identify requirements for a new commercial software implementation. The first step is to break down the business analysis deliverables into activities and tasks. Then, the business analyst will add an estimate of the time needed to complete the work.
Which type of estimation technique is the business analyst using?
Which type of estimation technique is the business analyst using?
Question 89
A project that was going well for the last few months has encountered a situation-regulatory authorities have deemed that the project does not meet their requirements. Although regulatory requirements were identified during an earlier phase of the project, there is no substantial evidence to prove that the requirements were formally rejected.
This could have been avoided if:
This could have been avoided if:
Question 90
A company has launched a new online sales application and engaged a focus group to test how quickly the customer could place an order. The focus group also provided feedback on their satisfaction.
Which metrics tool should the business analyst use to record the results?
Which metrics tool should the business analyst use to record the results?