Question 26

A company has just finished the development work for a new software sales tracking application and is in the process of validating that the new application meets all of the acceptance criteria defined for the business requirements. During the validation process, a stakeholder discovers that the application does not provide the selection criteria needed to produce the sales volume reporting required by the company's financial department. The business analyst for the project determines that the selection criteria needed was not specified in the system requirements or design specifications.
Which of the following tools and/or techniques might be used by the business analyst to determine how the selection criteria requirement was missed?
  • Question 27

    A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?
  • Question 28

    During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:
  • Question 29

    A business analyst is planning the business analysis activities for a new payroll project. Due to a tight timeline, the analyst advises stakeholders that the requirements sessions should begin as soon as possible.
    Which key factor drives the selection of business analyst activities to be included in the project?
  • Question 30

    Which of the following best describes the function of the requirements baseline?