Question 71
The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks:
Risk 1 has a US$500,000 potential cost increase, and a 60 day potential schedule slippage, with a 25% probability of occurring Risk 2 has a US$200,000 potential cost increase, and a 20 day potential schedule slippage, with a 60% probability of occurring Risk 3 has a US$1,200,000 potential cost increase, and a 90 day potential schedule slippage, with a 10% probability of occurring Risk 4 has @ US$600,000 potential cost increase, and a 70 day potential schedule slippage, with a 20% probability of occurring Using expected monetary value calculation, which risk has the greatest potential impact to cost and schedule?
Risk 1 has a US$500,000 potential cost increase, and a 60 day potential schedule slippage, with a 25% probability of occurring Risk 2 has a US$200,000 potential cost increase, and a 20 day potential schedule slippage, with a 60% probability of occurring Risk 3 has a US$1,200,000 potential cost increase, and a 90 day potential schedule slippage, with a 10% probability of occurring Risk 4 has @ US$600,000 potential cost increase, and a 70 day potential schedule slippage, with a 20% probability of occurring Using expected monetary value calculation, which risk has the greatest potential impact to cost and schedule?
Question 72
Joan is the project manager of the BTT project for her company. She has worked with her project to create risk responses for both positive and negative risk events within the project. As a result of this process Joan needs to update the project document updates. She has updated the assumptions log as a result of the findings and risk responses, but what other documentation will need to be updated as an output of risk response planning?
Question 73
Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board
agrees with you. What component of the change control system communicates the approval or denial of a proposed change request?
agrees with you. What component of the change control system communicates the approval or denial of a proposed change request?
Question 74
You are the project manager of a new project in your organization. You and the project team have identified the project risks, completed risk analysis, and are planning the most appropriate risk responses. Which of the following tools is most effective to choose the most appropriate risk response?
Question 75
A mobile operator wants to test a new network prototype before conducting full implementation on the entire network. What type of risk response strategy did the mobile operator choose?
Premium Bundle
Newest PMI-RMP Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PMI-RMP Exam! BraindumpsPass.com now offer the updated PMI-RMP exam dumps, the BraindumpsPass.com PMI-RMP exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PMI-RMP pdf dumps with Exam Engine here: