Question 36
During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the current customers electrical infrastructure. This event was not originally identified as a risk.
To maintain the project schedule, the project manager decides to purchase a new power adapter.
What type of response best describes this course of action?
To maintain the project schedule, the project manager decides to purchase a new power adapter.
What type of response best describes this course of action?
Question 37
Todd is the project manager of the EST project for his company. His organization has established certain rules in the enterprise environmental factors which affect the approach that Todd takes in managing his project. One of the rules requires Todd to consider the risk attitude of the stakeholders participating in risk analysis. Why must risk attitude be considered as a part of risk analysis?
Question 38
You work as a project manager for BlueWell Inc. You are performing the quantitative risk analysis for your project. One of the project risks has a 50 percent probability of happening, and it will cost the project
$55,000 if the risk happens. What will be the expected monetary value of this risk event?
$55,000 if the risk happens. What will be the expected monetary value of this risk event?
Question 39
Rex is the project manager of the BDF Project. This project will last for two years and has a budget of $2,345,000. Management has instructed Rex that the project must not go over budget as funds are very tight in the organization. During the project planning Rex and the project team discover a positive risk event to save $75,000. Rex wants to make certain that this risk event happens so which risk response method is most appropriate?
Question 40

A regional vendor for custom manufactured steel oil derricks is awarded a contract to design, manufacture, and install 40 offshore oil platforms. Installation of these derricks requires precision placement and stable seas for the transport and installation ships to properly install the deep water structure. It takes 65 days to transport the deep water structures for each platform from the manufacturing facility to the installation site at a cost of US$155,000 per day. The monsoon season runs from May to September each year and is a known risk for placement of the oil platforms. There is an incentive clause in the contract that will provide a USS1,500,000 payment, if all 40 platforms are in place and ready for use by 5 January 2016.
What is the probability of receiving this incentive?
Premium Bundle
Newest PMI-RMP Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PMI-RMP Exam! BraindumpsPass.com now offer the updated PMI-RMP exam dumps, the BraindumpsPass.com PMI-RMP exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PMI-RMP pdf dumps with Exam Engine here: