Question 41
Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project's success and do not believe that the benefits are significant.
What should the risk manager do?
What should the risk manager do?
Question 42
A risk manager works with the project team, senior management team, subject matter experts and other stakeholders to identify the project risks. Which of the following tools/methods from the risk management plan can be used to identify a risk, which is based on project objectives by category?
Question 43
Wendy is the project manager of the FBL project for your company. She has identified several risks within her project and has created a risk contingency reserve of $45,000 total. Her project is nearly complete and many of the risks have not happened in the project. What should Wendy do with the funds in the contingency reserve?
Question 44
Holly is the project manager of the GHH Project. During risk identification and the subsequent risk analysis process she has identified a risk with a high probability and high impact for her project. She and the stakeholder agree that the project management plan should be changed to eliminate the risk threat entirely.
What risk response has Holly used in this instance?
What risk response has Holly used in this instance?
Question 45
Which of the following processes looks at the complex web of actors, rules, conventions, processes, and mechanisms concerned with how relevant risk information is collected, analyzed and communicated, and how management decisions are taken?
Premium Bundle
Newest PMI-RMP Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PMI-RMP Exam! BraindumpsPass.com now offer the updated PMI-RMP exam dumps, the BraindumpsPass.com PMI-RMP exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PMI-RMP pdf dumps with Exam Engine here: