Question 56
A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
What should the project manager do next to avoid similar risks?
Question 57
Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?
Question 58
The risk manager evaluates two contractors, contractor A and contractor B, for a project with a finish date of 15 December. The contractors' bids are the same, including the cost. After performing a Monte Carlo assessment on the contractors' schedules, the risk manager returns the following information:

In order for contractor A to meet the finish date of 15 December, it will cost an additional US$750,000, and will not change the confidence level.
In order for contractor B to meet the finish date of 15 December, it will cost an additional US$600,000, and will increase the confidence level by 10%.
Which contractor should the risk manager select?

In order for contractor A to meet the finish date of 15 December, it will cost an additional US$750,000, and will not change the confidence level.
In order for contractor B to meet the finish date of 15 December, it will cost an additional US$600,000, and will increase the confidence level by 10%.
Which contractor should the risk manager select?
Question 59
A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.
What should the risk manager do?
What should the risk manager do?
Question 60
Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.
What should the project manager do next?
What should the project manager do next?
