Question 111

Company A sells a new machine to company B. During the risk assessment, the stakeholders of company A do not want the risk of transporting the machine from their facility. Instead, they want company B to take responsibility and liability once the machine leaves company A's facility.
What strategy is company A using to deal with the risk?
  • Question 112

    Which one of the following is the only output for the qualitative risk analysis process?
  • Question 113

    You are the project manager of the GHQ project for your company. You are working with your project team to prepare for the qualitative risk analysis process. Mary, a project team member, does not understand why you need to complete qualitative risks analysis. You explain to Mary that qualitative risks analysis helps you determine which risks needs additional analysis. There are also some other benefits that qualitative risks analysis can do for the project. Which one of the following is NOT an accomplishment of the qualitative risk analysis process?
  • Question 114

    During a major project review, the project manager discovers that large groups of internal management issues are obstructing progress. In reviewing the risk management plan, the project risk categories largely contain technical and customer relationship type risks. The project manager wants the risk management plan revised to account for these risk areas, particularly because the project has several more months before completion.
    Who should the project manager collaborate with to revise the risk management plan at this stage of the project?
  • Question 115

    You are the project manager of the GGK project for your company. The GGK project has a budget of $1,265,100 and is currently 40 percent complete. In this project, you elected to add labor to the project to increase the likelihood of completing the project early as the project was only scheduled to be 35 percent complete at this time. This positive risk response, while keeping the project ahead of schedule, has added significant costs to the project. You have already spent
    $575,000 to reach this point in the project. Management would like to know what your cost performance index and the schedule performance index is for this project. What are these values?