Question 151

Holly is the project manager of the GHH Project. During risk identification and the subsequent risk analysis process she has identified a risk with a high probability and high impact for her project. She and the stakeholder agree that the project management plan should be changed to eliminate the risk threat entirely. What risk response has Holly used in this instance?
  • Question 152

    A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.
    What should the project manager do to avoid this risk?
  • Question 153

    During a status meeting, a functional manager complains that the server backup failed, impacting the department. This was a known risk documented in the risk register as an accepted risk. After reviewing the meeting minutes, itis determined that the functional manager had not participated in the risk planning phase.
    Which of the identification methods should have been applied?
  • Question 154

    The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.
    What should the project manager do first?
  • Question 155

    Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.
    What will help calculate the impact?