Question 16

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges What two actions should the risk owner take? (Choose two.)
  • Question 17

    Which of the following is an input to identify risk?
  • Question 18

    A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described.
    What is critical for the risk manager to consider when describing the causes?
  • Question 19

    The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.
    What recommendation should the risk manager make to the project manager?
  • Question 20

    A six-month, US$1,2 million project is two months completed. The project has 3 high, 6 medium, and 2 low risks, with a 10% reserve for known risks, and a 5% reserve for unknown risks. Most of the project's reserves have not been spent. The risk manager, who is also the project schedule manager, establishes monthly risk management reviews to evaluate performance. So far, the project has missed 50% of the planned risk mitigation milestones.
    Based on this project data, what technique should the risk manager recommend to improve the risk management process?
  • Premium Bundle

    Newest PMI-RMP Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PMI-RMP Exam! BraindumpsPass.com now offer the updated PMI-RMP exam dumps, the BraindumpsPass.com PMI-RMP exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PMI-RMP pdf dumps with Exam Engine here:

    (336 Q&As Dumps, 40%OFF Special Discount: Exam-Tests)
    Other Version
    1953PMI.PMI-RMP.v2026-04-25.q187
    3656PMI.PMI-RMP.v2024-01-04.q117
    2589PMI.PMI-RMP.v2023-10-13.q118
    3797PMI.PMI-RMP.v2023-07-22.q124
    5130PMI.PMI-RMP.v2022-06-21.q189
    Latest Upload
    144VMware.3V0-12.26.v2026-11-27.q21
    211Microsoft.MB-335.v2026-11-27.q229
    201HP.HPE7-A03.v2026-11-27.q91
    165Anthropic.CCAR-P.v2026-11-27.q50
    181HP.HPE7-A06.v2026-11-26.q72
    303APA.CPP-Remote.v2026-11-25.q140
    228F5.F5CAB4.v2026-11-25.q74
    170VMware.3V0-25.25.v2026-11-25.q23
    256HP.HPE6-A86.v2026-11-24.q133
    258CTTAM.Civil-Engineering-Technology.v2026-11-23.q41