Question 836
A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation What should the project manager do next?
Question 837
During the execution phase of a project a new functional manager joins the company to replace the former functional manager During a monthly meeting, the new functional manager expresses confusion about the data provided in the meeting and asks for weekly reports via email because this project affects their department's work significantly After checking, the project manager finds out that the former functional manager did not receive the weekly email report.
What is the cause of this problem?
What is the cause of this problem?
Question 838
You are the project manager for a company that sells online music. The company is growing so well that the company has outgrown its I.T infrastructure. In fact, the company's current infrastructure is unable to handle the terabytes of music download each day. As a result, the company has decided to outsource its music download infrastructure to a third party content management vendor. The content management vendor will host the compressed music files across its geographically distributed web server farms, and handle all the logistics with music file downloads and data streaming. On your qualified sellers list, you have identified one potential vendor MusikCM. Your procurement department is conducting an independent estimate of costs of the proposals in order to compare the vendor prices. However, your procurement department has identified a large difference between the independent estimate and the proposed vendor cost. In which process is this taking place?
Question 839

Based on the project scheduled, how much float is there for activity number 4?
Question 840
What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?