Question 356

You are the Project Manager on a merger and acquisition project. Activity A (3 days) and activity B (4 days) can start immediately. Activity C (2 days) can start after A and B are complete. Activity D (5 days) can begin after activity B is complete. Activity E (6 days) can begin after activity B is complete. Activity F (4 days) can begin after activities C and D are complete. Activity G (5 days) can begin after activities D and E are complete. Activity H (4 days) can begin after activities F and G are complete. What is the critical path?
  • Question 357

    The project is going through Quality control. Which of the following are used to validate that the output is in compliance with the specifications of the work?
  • Question 358

    The zero defects concept
  • Question 359

    The project manager is given two teams that are restricted to working five days per week. The initial calculations give a project timeline of two weeks. However, one of the teams will only be available for two and a half days during week one due to a previous commitment. The timeline is revised to three weeks.
    What optimization technique was used to revise the timeline?
  • Question 360

    During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead handle this situation?