Question 1
Product testing is nearly complete when the project manager overhears a stakeholder mention that the company is likely to rebrand itself This would result in product redesign. After contacting the marketing manager to validate this, the project manager learns that a decision has not yet been made.
What should the project manager do?
What should the project manager do?
Question 2
Some members of a project team work from home. During a weekly video-conference. much time is lost due to disconnected or dropped participants, background noise, strong interference, or multiple people speaking simultaneously. People are becoming annoyed and ask not to participate.
What should the project manager do?
What should the project manager do?
Question 3
Which action is included in the Control Costs process?
Question 4
The table lists project activities with activities A and H as start and end activities.

What is the project's critical path?

What is the project's critical path?
Question 5
You have been hired as a project manager for a local bank. Bank wants to develop and design the custom online bill pay software so that its customer can pay bills online. You are ready to begin the activity duration estimates for your project.
Two years ago you were involved in prior project where a team of ten programmers were able to create similar bill pay software in 180 days. Therefore in estimating the duration of this new project, you decided to use 180 days as an estimate. This is an example of which type of estimating technique?
Two years ago you were involved in prior project where a team of ten programmers were able to create similar bill pay software in 180 days. Therefore in estimating the duration of this new project, you decided to use 180 days as an estimate. This is an example of which type of estimating technique?