Question 31

All of the following are sources of conflict EXCEPT:
  • Question 32

    An agile team meets at the end of a sprint to compile the retrospective. A team member mentions that the IT maintenance manager revealed that their team is unanimously opposed to the software platform change introduced in the previous sprint. The project manager discovers that the IT maintenance manager was defined as an external stakeholder in the stakeholder engagement plan.
    What should the project manager do to prevent further disruptions of this type?
  • Question 33

    The following is a network diagram for a project.

    The shortest non-critical path for the project is how many days in duration?
  • Question 34

    You are managing a project in a foreign country, where you realize that you will have to pay a fee to some government agencies to get your work done. You should:
  • Question 35

    With respect top cost of quality, which of the following individuals suggested that 85% of the cost of quality is a management problem?