Question 321

In your project, there have been several changes in the cost and schedule estimates and the original estimating assumptions are no longer valid. What is the Estimate at Complete for your project?
BAC = $ 300,000 AC = $ 100,000 EV = $ 150,000 CPI = $ 1.2 ETC = $ 120,000
  • Question 322

    Which of the following is contained within the communications management plan?
  • Question 323

    You are a project manager at java ice cream factory. You are currently supervising the manufacturing of new flavor ice cream java bean, burgundy crunch. The manufacturing of this flavor was proceeding as planned, until a manufacturing error occurred that requires corrective
    action to be taken. Ironically the manufacturing error resulted in a new variant of the flavor.
    Product team really thinks that flavor would be a success in a marketplace. They have asked you to cancel the corrective action, and integrate this serendipitous discovery in the manufacturing process. As a project manager you have realized that this has resulted in a change in project scope. Which of the following statement are true?
  • Question 324

    A quality manager informs a project manager that their team is performing tasks that are not part of the project management plan. A project team member notes that a task was added after a discussion with the customer.
    What should the project manager do?
  • Question 325

    Drag the characteristics of the stage on the left to the correct Tuckman Ladder stage on the right