No.# Answer: B. The duration of the project will increase by 2 months
Explanation
The critical path is the longest sequence of dependent tasks from the start to the finish of a project, determining the shortest possible project duration.
Tasks on the critical path have zero float (or slack). Any delay in a critical task will cause the entire project to be delayed by an equal amount of time.
The provided table lists Earned Value Management (EVM) data (Planned Value, Actual Cost, Earned Value) which helps track performance against a baseline, but does not provide the task dependencies or durations needed to calculate the critical path directly.
The question assumes that the task 1->2 is a critical task. Therefore, a two-month delay in this task directly increases the project's overall duration by two months.

Geoff  
Oct 19, 2025

Do not hesitate, try it. I passed just. Very great.Valid

Martina  
Sep 22, 2025

PMP dumps helped me a lot, pass my exam yesterday. Most questions of PMP dumps are same to the actual test. Good Luck everyone.

Aymenk  
Jul 09, 2025

Pmp questions

Add Comments

Your email address will not be published. Required fields are marked *

insert code
Type the characters from the picture.