Identify the missing words in the following sentence.
Configuration management typically includes [ ? ] as one of the five core activities.
Which of the following statements about lines of authority and reporting are true?
1.The Project Manager has day-to-day control for a management stage within the limits laid,
2.If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.