At the stage 2 boundary, the project manager recommends adding the replacement subcontractor's account manager to the project board to represent supplier interests during stage 3.
Which practice is being applied in 'managing a stage boundary'?
During the 'initiating a project' process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.
Is this an appropriate approach to leading successful change, and why?
PROCESSES
During the 'starting up a project' process, the Head of the Portfolio Office explains to the prospective project executive that LouisShopping is strategically important to the LOB portfolio, must support increased business opportunities and is expected to open by the end of financial year three.
During which activity should this clarification of the mandate and business expectations take place?
During stage 3, several BuildyBrick subcontractors are working on different work packages. The project manager is concerned that lessons identified by one team will not reach the others and could lead to rework, delay or additional cost. The project manager therefore holds a fortnightly cross-team 'lunch and learn' session.
Is this an appropriate application of the 'learn from experience' principle, and why?