Question 6

How is the 'tailor to suit the project' principle applied in an agile context?
  • Question 7

    What is an epic?
  • Question 8

    Why is Lean Startup included in the 'starting up a project' process in PRINCE2 Agile?
  • Question 9

    What needs to happen when new detailed requirements are added to a timebox?
  • Question 10

    Which TWO project board responsibilities are specifically assigned to the senior user?
    1) Demonstrating the achievement of benefits.
    2) Specifying the needs of those impacted by the outputs.
    3) Balancing business, user and supplier demands.
    4) Ensuring that the project delivers value for money.