Question 86
Which statements about quality assurance and project assurance are CORRECT?
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used
Question 87
Which theme verifies that a project's products are fit for purpose?
Question 88
How is a Benefits Review Plan used in the Closing a Project process?
Question 89
Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?
Question 90
Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?